Installing a new system or replacing your old septic system
HOW TO OBTAIN a SITE EVALUATION, SEPTIC PERMIT, AND A LICENSED SYSTEM CONTRACTOR.
Step 1 Have a site evaluation performed by a licensed class D soil scientist to determine what type of disposal system, under current regulations, can be sited on the parcel.
^ The soil scientist performs field work, prepares the site evaluation report and submits the report to
the Department of Natural Resources (DNREC), with the appropriate fee, for approval.
^ DNREC reviews the report and approves/denies the site evaluation within 10 working days of receipt.
^ The site evaluation is then mailed to the owner or authorized agent.
Step 2 Hire a licensed system designer to design the OWTDS and obtain a system permit.
^ Select a Class B designer for a gravity system.
^ Select a Class C designer for engineered and pressure dosed systems.
^ All designs are submitted to DNREC with appropriate fee. Once approved the system is permitted.
^ Gravity permits take approximately 10 working days from time of receipt to final approval.
^ Engineered permits take approximately 20 working days from time of receipt to final approval.
Step 3 Choose a licensed Class E system contractor to install the OWTDS.
Our Services
- Septic tank, grease trap, & holding tank pumping and cleaning
- Septic system installation & repair (Gravity, LPP, Pressure Dosed, Mound, Peat, Micro-Drip, etc.)
- Septic system inspection- DE licensed Class H
- Well Installations
- Water Treatment Systems
- Drinking water tests
- Tank riser & outlet filter installations
- Tank, d-box, and drainfield location
- No Charge for Mileage
- Landscape Friendly Pumping- WE CARRY EXTRA HOSE
Licensed in DE & MD Counties
Serving All of Sussex County
FREE Back Flushing Upon Request
Licensed For Holding Tanks
SEAFORD/BRIDGEVILLE/GREENWOOD: (302) 629 - 6221 Or (302) - 629-4327
LEWES/MILTON/REHOBOTH/GEORGETOWN: (302) 856 - 3898
LAUREL/MILLSBORO: (302) 875 - 8831
DELMAR/SALISBURY: (302) 846 - 3121